Title: Approval of an Infrastructure Improvement Agreement With Mountain Shadows Resort ("Resort") Providing For Payment By The Resort Of The Town's Design And Construction Costs For A New Median And Deceleration Lane On Lincoln Drive To Allow Left-Turn Access For Westbound Traffic Into The Resort's Westernmost Driveway
Attachments: 1. MTS Agreement - Council Meeting 062520 (FINAL), 2. Public Comment Received May 24 2020

TO:                                             Mayor and Town Council

 

FROM:                      Jill Keimach, Town Manager

Andrew Miller, Town Attorney

Debby Robberson, Assistant Town Attorney

Jeremy Knapp, Community Development Director

                                                                     

DATE:  June 25, 2020

 

CONTACT:

Staff Contact Andrew Miller, 480-348-3691

End

 

AGENDA TITLE:

Title

Approval of an Infrastructure Improvement Agreement With Mountain Shadows Resort (“Resort”) Providing For Payment By The Resort Of The Town’s Design And Construction Costs For A New Median And Deceleration Lane On Lincoln Drive To Allow Left-Turn Access For Westbound Traffic Into The Resort’s Westernmost Driveway

Body

 

RECOMMENDATION:

Recommendation

Authorize the Town Manager to execute an infrastructure improvement agreement with Mountain Shadows Resort.

Background

 

BACKGROUND:

The Town has a planned capital improvement project, the Lincoln Drive Median Improvements Project (LDMI Project), to modify, add and remove medians on Lincoln Drive to improve safety, traffic operations, and landscaping.  The LDMI Project encompasses medians from the Town’s western boundary to Mockingbird Lane. The LDMI Project was previously presented at the 11/21/19 and 2/27/20 Town Council Work Study meetings, and the construction contract was presented at the 5/28/20 Work Study meeting.  This matter was also discussed during a Work Study meeting on 06/11/20.

 

A troublesome traffic pattern has developed over the years on Lincoln Drive adjacent to the Resort.  Westbound vehicles desiring to enter the Resort often drive past the current entrance at Mountain Shadows Private Drive and make a U-turn on Lincoln Drive just west of the Resort to “backtrack” and enter the Resort. 

 

To improve Resort guest access and traffic movements on this portion of Lincoln Drive, the Resort previously applied for, and the Planning Commission approved, a minor amendment to the Resort’s 2013 SUP. This minor amendment allows revised access to the Resort from Lincoln drive (left-turn access for westbound traffic via a median break and deceleration lane), but it does not otherwise change any conditions or entitlements of the Resort’s 2013 SUP.  Nor does the proposed Infrastructure Improvement Agreement modify any of the entitlements for the Resort property.

 

The Resort requested that the Town include a revised access to allow left-turn access for westbound traffic in the LDMI Project.  Under the proposed Infrastructure Improvement Agreement (“Agreement”), if the Town Council approves a construction contract for the LDMI Project, the Town will design and construct the median configuration and deceleration lane (“Left Turn Plan”) as part of the LDMI Project, and the Resort will pay the costs associated with the design and construction.  The Agreement requires the Resort to deposit funds to cover the estimated design and construction costs of the Left Turn Plan prior to the start of construction, and such funds will be available to the Town to draw upon.  If actual costs to construct the left Turn Plan exceed the estimated costs, the Resort is obligated to pay the additional amount needed.  If the estimate is more than the actual cost, the Town is obligated to refund any amounts not used for the Resort’s portion of the LDMI Project.

 

In the event the Town does not move forward with the LDMI Project, the Resort has the option to independently construct the revised access.  The Resort is obligated to pay the Town for the design costs prior to obtaining a permit for the construction and the construction must occur before the Town resurfaces Lincoln Drive (mill and overlay), which is currently planned for the summer of 2021. 

 

Council consideration of a construction contract for the LDMI Project is currently planned for the Council meeting on 6/25/20.  If the construction contract is approved, staff anticipates construction would begin on the LDMI Project as soon as possible (mid to late July).   

 

 

Next Steps

It is recommended that the Council approve the Infrastructure Improvement Agreement between the Town and MTS Resort Owner, LLC.

 