TO: Mayor Jerry Bien-Willner and Town Council Members
FROM: Jill Keimach, Town Manager
Brent Skoglund, Public Works Director
Jerry Cooper, Public Works Superintendent
DATE: January 9, 2020
DEPARTMENT:
Public Works Department
STAFF CONTACT:
Staff Contact Brent Skoglund, Public Works Director 480 348-3540
Jerry Cooper, Public Works Superintendent 480 348-3589
End
AGENDA TITLE:
Title
Implement the FY2019-20 Pavement Maintenance Program by Approving the Funds from Budget Line Item 20-40-871 Pavement Maintenance Program to M.R. Tanner in the amount of $1,599,526.10
Body
RECOMMENDATION:
Recommendation
Award the following funds to M.R. Tanner in the amount of $1,599,526.10 for a full mill and 11/2 asphalt overlay in Maintenance Districts 5 and 13 and to crack seal and apply Polymer Modified Master Seal (PMM) in Maintenance Districts 7 & 8.
Background
SUMMARY STATEMENT:
It is recommended that M.R. Tanner be awarded $1,599,526.10 to complete the FY2019-20 Pavement Maintenance Program that includes the following projects:
Maintenance District 5 - It is recommended that this Maintenance District receive a full mill and 1 1/2 asphalt overlay on the selected 5.4 linear miles of streets. The streets within in this District have an average Pavement Condition Index (PCI) of 64 which require a full mill and asphalt overlay per the current pavement management program.
Maintenance District 7 - It is recommended that this Maintenance District receive crack seal and an application of a high-density mineral bond, PMM, on the selected 7.3 linear miles of streets. The selected streets have an average Pavement Condition Index (PCI) of 72 which require crack seal and a PMM surface seal per the current pavement management program.
Maintenance District 8 - It is recommended that this Maintenance District receive crack seal and an application of a high-density mineral bond, PMM, on the selected 6.9 linear miles of streets. The selected...
Click here for full text