Paradise Valley Legistar Banner
File #: 19-385    Version: 1 Name:
Type: Study Session Item Status: Agenda Ready
File created: 10/18/2019 In control: Town Council
On agenda: 10/24/2019 Final action: 10/24/2019
Title: Project update for Lincoln Dr, Mockingbird Ln, and Indian Bend Rd Improvements
Attachments: 1. PowerPoint Presentation - CMAR FINAL 102219

TO:                                             Mayor Bien-Willner and Town Council Members

 

FROM:                      Jill B. Keimach, Town Manager

                                          Paul Mood, Town Engineer

                                            Jason Harris, Capital Projects Administrator

 

DATE:                     October 24, 2019

 

DEPARTMENT: Engineering

 

Staff Contact Jason Harris, 480-348-3622

End

 

AGENDA TITLE:

Title

Project update for Lincoln Dr, Mockingbird Ln, and Indian Bend Rd Improvements

Body

 

RECOMMENDATION:

Discussion with possible direction of construction manager at risk construction contract with Achen-Gardner Construction LLC and construction management services contract with Wood Patel & Associates.

 

SUMMARY STATEMENT:

Construction is anticipated to begin in January 2020 and be completed by the end of February 2021.

 

BUDGETARY IMPACT:

This is a discussion item only. Please refer to agenda action items 19-378 (Achen-Gardner contract) and 19-379 (Wood Patel contract) for the budgetary impacts.

 

ATTACHMENT(S):

Presentation