Paradise Valley Legistar Banner
File #: 19-379    Version: 1 Name:
Type: Contract Status: Agenda Ready
File created: 10/17/2019 In control: Town Council
On agenda: 10/24/2019 Final action:
Title: Award of Construction Management Services Contract for Lincoln Dr, Mockingbird Ln, and Indian Bend Rd Improvements
Attachments: 1. Contract 20-099 - Wood Patel.pdf

TO:                                             Mayor Bien-Willner and Town Council Members

 

FROM:                      Jill B. Keimach, Town Manager

                                          Paul Mood, Town Engineer

                                            Jason Harris, Capital Projects Administrator

 

DATE:                     October 24, 2019

 

DEPARTMENT: Engineering

 

Staff Contact Jason Harris, 480-348-3622

End

 

AGENDA TITLE:

Title

Award of Construction Management Services Contract for Lincoln Dr, Mockingbird Ln, and Indian Bend Rd Improvements

Body

 

RECOMMENDATION:

Recommendation

Authorize the Town Manager to execute the construction management services contract with Wood Patel & Associates in the amount not to exceed $453,860.00

Background

 

SUMMARY STATEMENT:

In anticipation of the Construction Manager at Risk (CMAR) contract being awarded and construction to commence thereafter, the Town is in need of a firm to assist staff with the construction management, including but not limited to, safety monitoring, documenting the work, and inspections for the duration of the construction project. The firm will act as the “Owner’s Representative” in the capacity of a resident engineer to interact with the CMAR (contractor) and the designer to engage communication and problem solving as needed. Specific duties of the firm are provided in the attached contract Exhibit A.

 

Construction is anticipated to begin in January 2020 and be completed by the end of February 2021. The proposed contract includes an allowance of $65,000 which may be used for additional inspectors, night/weekend inspections, etc. Use of this allowance requires approval by Town staff.

 

This contract is being funded with funds collected from Five Star Development (Five Star). The Town collects a 10% Town Management Fee per Five Star’s Development Agreement section 2.3.5.6. The fee is calculated based on 10% of Five Star’s cost share for the design and construction of the project. The Town will utilize a portion of these funds to augment staffing needed to perform the construction management services required for the Lincoln Dr, Mockingbird Ln, and Indian Bend Rd improvements (project) encompassing the Five Star Development Area.

 

BUDGETARY IMPACT:

The budget impact for the award of this contract is as follows:

CIP Project #2016-14                     $453,860 Construction Administration

 

Award will be contingent on the award of the Construction Manager at Risk (CMAR) contract for this project being considered under a separate agenda item no.19-378.

 

 

ATTACHMENT(S):

Contract No. 20-099