Title: FY 2018 Budget Overview and Capital Improvement Program
Attachments: 1. 030917 FY 2018 Budget Presentation, 2. General Fund Revenue Forecast for 030917 Study Session

Memo

 

TO:      Mayor Collins and Town Council Members

 

FROM: Kevin Burke, Town Manager

                       Dawn Marie Buckland, Director of Administration & Government Affairs

 

DATE: March 9, 2017

 

DEPARTMENT: Administration and Government Affairs Department

 

Staff Contact

Dawn Marie Buckland, 480.348.3555

End

 

AGENDA TITLE:

Title

FY 2018 Budget Overview and Capital Improvement Program

Body

 

Council Goals

Develop a long term sustainable budget; Address police pension funding requirements; Ensure financial health without compromising Town values; Identify a funding mechanism for CIP

 

SUMMARY STATEMENT:

In local government, the budget is not only a financial plan, but also an operations guide, a communications device, and a policy document.  As such, it is an integral part of policy discussions with Council throughout the year.

 

The March 9 study session will provide an overview of economic forecasts, local conditions, and the Town’s organizational goals that provide the basis for the budget and long range financial plan.  The bulk of the study session will focus on the Town’s capital improvement program.

 

The Capital Improvement Plan (CIP) is a multi-year plan which identifies and prioritizes the Town’s anticipated capital needs. The CIP identifies which projects will be constructed over the next five years, their impact to the community and quality of life, and how they will be funded.  It is adopted as a part of the budget resolution and presented as a separate section of the budget document.  Attached please find a DRAFT CIP for the next five years.  This Study Session will review projects with Mayor & Council to determine continued interest, appropriate scope, desired timing, and cost considerations. 

 

The Town decides the cost threshold and types of projects.  At this time, staff recommends projects greater than $100,000 and a useful life of at least two years (excluding vehicles and other rolling stock) which would result in the following types of projects:

                     Renewal and Replacement of Existing Infrastructure

                     Facility Improvements

                     Streets/Sidewalks/Paths (Pedestrian and Bicycle)

                     Electric Utility Undergrounding

                     Stormwater/Drainage

                     Technology

                     Sustainability

                     Wastewater Utility

 

Projects are identified, scoped, and ranked using an annual 4 step process:

1.                     Identify Needs/Projects.

2.                     Determine Costs

3.                     Prioritize Projects

4.                     Develop Financing Strategies

 

STEP 1:  Identify Needs/Projects

 

The objective of this step is to compile a “laundry list” of all possible projects that will later be prioritized.  The projects come from many sources of information including:

                     Citizens

                     Town Council

                     Strategic Plan

                     General Plan

                     Master Plans

                     Staff

 

STEP 2:  Determine Costs

 

For each project identified in Step #1, detailed information about the project will be gathered and will include:

                     Purpose/Objective

                     A description of the project

                     Its relationship to the General Plan (e.g. sustainability)

                     Timeline

                     Operating Impacts (Cost or Savings)

                     Map/Location of Project

                     Project Scope broken down into land, design, construction, and contingency

 

STEP 3:  Prioritize Projects

 

The Capital Improvement program is based on this prioritization process.  Projects are prioritized based on the Town’s critical objectives and strategies, the Town’s 2012 General Plan, special studies and reports, Town Council and department priorities, and anticipated funding sources.  This evaluation process is very much an iterative process using a numeric rating system based on the following evaluation criteria.  Projects are then evaluated on the following project prioritization matrix.

 

Town’s Critical Objectives - 40% - (2012 General Plan) If a capital project directly addresses a Town’s critical objective or includes health-related environmental impacts like reductions in traffic accidents, injuries, deaths, or health hazards due to poor water quality, the relative attractiveness of that project increases.

                     Increase in public health

                     Increase in public safety

                     Identified in General Plan

                     Consistent with vision statement

                     Consistent with annual work plan

                     Specific request of the Town Council

 

Costs - 30% - This represents the annual total costs, including future year capital costs.  Also to be considered is whether the proposed project will reduce future capital costs, for example, a rehabilitation project that averts a more expensive, subsequent replacement, and the extent of such savings.  Also to be considered is changes in revenues or funding from outside participants, such as grants or cost sharing, which may be affected by a project. Deferring capital projects is tempting for hard-pressed governments, but an estimate of the possible effects, such as higher future costs and inconvenience to the public, provides valuable guidance in proposal assessment.

                     Cost sharing / grant / outside funding

                     Source of higher revenue

                     Maintain, replace or expand an existing asset

                     Lower operating cost

                     Lower future capital cost

                     Implication of deferring the project

 

Community/Citizen Benefits, Environmental and aesthetics - 20% - Economic impacts such as property values, the future tax base, and the stabilization (or revitalization) of neighborhoods.  A criterion for other significant quality-of-life related impacts; this includes community appearance, noise, air and water pollution effects, damage to home, etc. Such impacts may apply more to capital projects related to new development than to infrastructure maintenance though deteriorating structures can adversely affect the community.

                     Stabilize or Improve neighborhood(s)

                     Improve quality of life for residents

                     Improves community appearance

                     Improves recreational/cultural opportunities

                     Improve environmental protection effort

                     Assists in elimination of slum and blight conditions

 

Distributional Effects - 10% - Estimates of the number and type of persons likely to be affected by the project and nature of the impact - for instance, explicit examination of project impact on various geographical areas.  Equity issues are central here - who pays, who benefits. Has the Town made a significant investment in this project within the last five years?

                     Town wide improvement

                     Benefits large portion of Town

                     Investment made by the Town in the last five years

                     Investment made by the Town to meet legal obligation

                     Project that has the support of another community or agency

                     Inter-jurisdictional benefit will be achieved

 

After all proposed projects are prioritized using these four criteria and 24 factors, the list will be reviewed from two more viewpoints: 1) does the list stand an “intuitive check”? Do projects fall in the priority order that was “anticipated”? And (2) are there any linkages between projects?  Are any projects related to each other geographically, or otherwise, such that having them accomplished concurrently would be advantageous? What about sequencing or timing?  Are any projects dependent on the completion of other projects?  Adjustments to the priority list may be necessary dependent on this final review.

 

STEP 4:  Develop Funding Strategies

As there are always more needs than resources, funding strategies will determine the final list of recommended projects. This step involves policy input from the Town Council and may result in modifying or creating new financial policies when it makes sense to do so.  Because the CIP is primarily funded from the Operating Budget, two key questions must be addressed:

1.                     How should existing operating revenues be allocated?

2.                     Are existing operating revenues enough?

 

Staff will discuss the capital improvement project requests at the March 9, 2017 study session, and will follow up with operating budget discussions on April 14, 2017.

 

 

ATTACHMENT(S):

Presentation including CIP project listing

10-Year operating forecast