TO: Mayor Bien-Willner and Town Council Members
FROM: Jill B. Keimach, Town Manager
Paul Mood, Town Engineer
Jason Harris, Capital Projects Administrator
DATE: June 13, 2019
DEPARTMENT: Engineering
Staff Contact Jason Harris, 480-348-3622
End
AGENDA TITLE:
Title
Award of Construction Contract for Town Hall Remodel
Body
RECOMMENDATION:
Recommendation
Authorize the Town Manager to execute the construction contract with Core Construction in the amount not to exceed $574,075, and to waive the 14-day wait period to sign the agreement.
Background
SUMMARY STATEMENT:
In 2016, the Town initiated a space needs assessment which analyzed Town Hall, Public Works/Engineering, and the Public Safety buildings for both the current and future needs. The objective was to understand the space required to provide efficient and effective public services, account for anticipated growth, and provide space for additional records required to be retained under state law.
The space needs assessment team looked at the buildings in their entirety with complete operations in mind and worked to identify opportunities to efficiently leverage the space identified. The Town engaged DWL Architects to complete this task and to address the issues of the Town Hall's lobby and the immediate need for designated and consolidated office space for IT staff, while maintaining a Community Room public space.
Staff presented progress updates and sought Council's input during study sessions held on March 28 and on April 25, 2019. Subsequently, DWL has completed the design for the Town Hall Remodel and Core Construction has obtained bids for construction.
The attached linking agreement allows the Town to enter into a construction contract with Core Construction using an existing Job Order Contract with the City of Peoria ("piggyback").
Project schedule
June 2019 Order long-lead items (air handler, partition doors, etc.)
September Begin construction
December End construction
...
Click here for full text